Relevant information for contractors about immediate procurements (click here for more information)

 

No.

Projects (responsible body: Railway infrastructure directorate of AB „Lietuvos geležinkeliai")

Project duration (start and finish date)

Project costs, Eur (excl. VAT)

Total:

752.556.385,96

Total CEF projects:

255.661.517

1.

Rail Baltica railway line Lithuanian and Poland state border - Kaunas:

2017-2020

76.786.358

1.1.

Preparation of technical documentation for electrification of section PL/LT state border – Marijampolė –Kazlų Rūda – Kaunas*

2018-2020

3.000.966

1.2.

Preparation of spatial planning documentation for straightening of section PL/LT state border – Kaunas*

2017-2019

1.313.000

1.3.

Study on upgrading the 1435 mm gauge railway line in section PL/LT state border – Kaunas (Palemonas) to traffic codes P2 and F1 (of INF TSI) and Global project standards

2017

650.000

1.4.

Installation of ERTMS 2.3.0d (or higher) version in Rail Baltica section Lithuanian and Poland state border – Kaunas*

2018-2020

15.080.000

1.5.

Installation of signalling, traffic management and related systems in 1435 mm wide gauge section Lithuanian and Poland state border – Kaunas*

2018-2020

56.742.392

2.

Rail Baltica railway line Kaunas – Lithuanian and Latvian state border:

2017-2020

178.875.159

2.1.

Land expropriation for construction of 1435 mm wide gauge railway in section Kaunas – Lithuanian and Latvian state border

2017-2018

13.083.590

2.2.

Study of archaeological and cultural heritage objects (Kaunas – Lithuanian and Latvian state border)

2017-2019

865.440

2.3.

Preparation of technical documentation for construction of 1435 mm wide gauge in section Kaunas – Lithuanian and Latvian state border**

2018-2019

14.815.314

2.4.

Construction of 1435 mm wide gauge double track in section Palemonas-Kalnėnai**

2019-2020

13.315.815

2.5

Construction of 1435 mm wide gauge double track railway bed in section  Kaunas (Palemonas) – Panevėžys – Lithuanian and Latvian state border**

2019-2020

131.190.000

2.6.

Project administration and management, maintenance, communication and public relations

2017-2020

5.605.000

Total Cohesion fund projects:

472.894.868.96

3.

Electrification of  Kena – N. Vilnia section

2014-2018

26.766.234,11

4.

Construction of the second rail track on the line Telsiai-Lieplauke

2015-2019

51.837.019,52

5.

Construction of the second track of IXB Corridor Vilnius Bypass Pusynas- Paneriai

2016-2019

28.892.215,33

6.

Vilnius railway junction electrification

2014-2021

48.102.800

7.

Electrification of Kaišiadorys - Radviliškis section

2017-2021

124.109.800

8.

Electrification of Radviliškis-Klaipėda (Draugystės st.) section***

2018-2021

160.359.500

9.

Expansion of Klaipeda railway junction. Stage 2. Pauostis yard reconstruction***

2019-2021

32.827.300

Total European regional development fund projects:

24.000.000

10.

Implementation of noise-reducing measures

2017-2020

24.000.000

 

*- RB Rail AS responsible for the preparation of the feasibility study (1.3). The study is aimed to provide best feasible and optimal option on how current railway line PL / LT – Kaunas will be modernized to meet the technical requirements of Rail Baltica global project. Results of the study can influence implementation and planning of other related activities.

**-Rail Baltica 1435 mm gauge section Kaunas - Lithuanian and Latvian border construction works will begin after the completion of land expropriation-related activities (section 2.1.).

***- Project implementation planned only after EU structural funds financial assistance is guaranteed.

 

Updated on 2017-06-06